Meyers Pool update (may open by Nov. 12th)

Executive Director Miles has selected Saunders Construction for the Phase 1 repairs for Meyers Pool. We have started the process and will work through the details for timing the project over the next few days. Saunders has indicated we should be able to open the pool by Nov.12. Of course that is assuming there are no surprises with the construction once we get into the work.

Saunders has already ordered the steel fabrication, our staff has begun the process of creating an accessible work environment for the construction crews, and we are taking steps to protect the water elements from construction debris,  etc.

Apex PRD board president Jim Whitfield

This is how government should work at all levels